What does the acronym RACI stand for in project management?

  1. Responsible, Approve, Consult, Inform

  2. Responsible, Accountable, Consulted, Informed

  3. Review, Approve, Control, Integrate

  4. Report, Analyze, Communicate, Implement

The correct answer is: Responsible, Accountable, Consulted, Informed

The acronym RACI stands for Responsible, Accountable, Consulted, and Informed, which is a framework used in project management to clarify roles and responsibilities within a project or process. In this model: - "Responsible" refers to the individuals or teams who perform the actual work to complete a task or deliverable. They are the ones executing the tasks and ensuring that work is done. - "Accountable" indicates the person who is ultimately answerable for the activity or decision. This role holds the authority over the process and ensures that the responsibilities are fulfilled, and the task meets the objectives. - "Consulted" encompasses those whose expertise or feedback is sought during the project. These stakeholders provide input that can greatly influence the outcome, and there is typically a two-way communication with them. - "Informed" includes those who need to be kept updated on progress or decisions but do not actively contribute to the tasks. This ensures that all relevant parties are aware of the developments without having direct involvement. This structured approach aids in eliminating confusion and ensuring that everyone knows their role, which is vital for effective project execution. Other options presented do not accurately represent the roles and responsibilities framework central to the RACI model.